What's going on with Cedar Brook Lane's water tower?

Can you find out what the plan is concerning the water tower on Cedar Brook Lane? There have been many people out on the property taking photographs. Ginny on Cedar Brook Lane.

A $238,000 project to paint and clean the water tower on Cedar Brook Lane should start soon, said Jack Meyers, Erie County's environmental services director.

"The need is for health, safety and aesthetics," Meyers said. "it has not been painted for 20 years, and that is the service life of new tank paint. If you go by it, you will see peeling paint and rust."

In the bids, the contractor can choose to either start on July 29, 2013 or April 1, 2014. The project should take 120 days to complete.

The Mailbag is a daily feature on SanduskyRegister.com. Every weekday at noon, we will post one question-and-answer from a resident. To ask a question, send a letter to The Mailbag at 314 W. Market St., or e-mail mailbag@sanduskyregister.com. Please include your first name and a location in the e-mail, e.g. “John from Decatur Street."